PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 25

You are an Agile team leader for Table Inc. Recently you’ve noticed some of your stakeholders are not as engaged as you think they should be. Which of the following options would be best to help improve their engagement?
  • A Reports any team member who is not staying engaged to the member’s manager
  • B Reports on benefits or issues regarding specific stakeholder involvement in status reports
  • C Doesn’t extend an invitation to any member who is not engaged in subsequent meetings
  • D Replaces the first team member who is not staying engaged to set precedence
Reveal correct answer

Correct answer: B

Explanation

To ensure stakeholder engagement, an Agile team leader will report on stakeholders’ contributions in a status or steering committee report.The other responses are incorrect. Replacing, reporting, or excluding a team member (stakeholder) who isn’t staying engaged is not the appropriate approach in this situation.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need