PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 12

You have been assigned as a trainer to teach new project managers about project approaches. In your first week, you describe what a Hybrid life cycle is. All of the following are false statements about Hybrid life cycles except:
  • A A Hybrid life cycle approach can be used when there is uncertainty, complexity, and risk
  • B A Hybrid life cycle needs to fully embody the Agile mindset, values, and principles
  • C A Hybrid life cycle is a combination of predictive, iterative, and Kanban approaches
  • D A Hybrid lifecycle fulfills the principles of the Agile Manifesto during the predictive part of the project
Reveal correct answer

Correct answer: A

Explanation

A Hybrid life cycle approach can be used when there is uncertainty, complexity, and risk is the correct answer.A Hybrid life cycle approach does not fully embody the Agile mindset values and principles. A Hybrid life cycle is not necessarily a combination of predictive, iterative, and Kanban methodologies. There is no stipulation that a Hybrid lifecycle must fulfill the principles of the Agile Manifesto during a predictive part of a project.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need