Question 84

You are the project manager of the NHQ Project for your company. You are working with your project team and the project sponsor to create a stakeholder management strategy. You want to determine the needed level of interaction among the project stakeholder. What document will best help you complete this task?
  • A Project charter
  • B Stakeholder registry
  • C Stakeholder management plan
  • D Project management plan
Reveal correct answer

Correct answer: C

Explanation

The stakeholder management plan is an input to management stakeholder engagements. This plan defines the needed levels of interactions of the project stakeholders. 1 is incorrect. The project charter authorizes the project and the project manager, but it doesn’t define the interactions among the project stakeholders. 2 is incorrect. The stakeholder registry defines the project stakeholders, their communication preferences, and project concerns. 4 is incorrect. The stakeholder management plan is part of the project’s management plan, but this isn’t the best answer for the question as the stakeholder management plan is most specific.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need