You are the project manager for your organization. You have just been assigned a new project with a predetermined budget of $250,000. This is an example of which one of the following?
- A Constraint
- B Assumption
- C Expert judgment
- D Functional structure
Reveal correct answer
Correct answer: A
Explanation
A predetermined budget is a project constraint. 2 is incorrect because this is not an example of an assumption. 3 is incorrect because this is not an expert judgment. 4 is also incorrect because this is not an example of a functional structure.Discussion