Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 67
A unique car dealership sells vehicles solely by a smartphone application. The application has succeeded in its beta testing phase but still requires an official launch to test the application in all markets across the United States. The application will have several different sections based on the market research and will have phases dispersing it in various locations. The dealership hired a project manager experienced in formal risk management explicitly for this project. What does the project manager's primary focus need to be as they tailor this project?
- A Development of the project
- B The complexity of the project
- C Importance of the project
- D Size of the project
Reveal correct answer
Correct answer: D
Explanation
The project manager will be tailoring the project according to its size. More extensive projects usually need a more formal risk management approach, while smaller, low-priority projects do not. The project's development refers to a waterfall, predictive, or agile approach and does not apply to the question. When the organization considers a task essential for opportunities, investment, reputation, and other considerations, it will warrant a well-thought-out project management risk approach regarding the importance of the project. As for complexity, a complex project often has many uncertainties that need to be addressed in the risk management approach. PRM11.5.134Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.