Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 62

Which of the following is not an input to plan cost management?
  • A Organizational process assets
  • B Project management plan
  • C Project charter
  • D Cost management plan
Reveal correct answer

Correct answer: D

Explanation

The cost management plan is the output of plan cost management. The project charter, organizational process assets, and the project management plan are all inputs to plan cost management. PCM7.2.229