While working on his current project, Matthew compares the planned usage of a resource to its actual use. What project resource management process is Matthew completing?
  • A Estimate activity resources
  • B Acquire resources
  • C Control resources
  • D Plan resource management
Reveal correct answer

Correct answer: C

Explanation

Monitoring the plan compared to the actual use of resources is done during control resources. If a variance needs to be corrected, corrective actions are taken as a part of control resources. Acquiring resources is about obtaining human and physical resources for the project and happens before any actual usage information can be captured. Estimating activity resources is about estimating time for team members and the type and quantity of physical resources for the project, which happens before any actual usage information can be captured. Plan resource management precedes all other project resource management processes before any actual usage information can be captured. PRM9.1.250

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need