Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 52

You are the project manager for your organization and you’re examining several projects you’re managing for your company. In your analysis you’ve noticed that one of your projects has an SPI of .80. A project with an SPI of .80 means what?
  • A The project is behind schedule.
  • B The project is ahead of schedule.
  • C The project is losing money.
  • D The project is 80 percent complete.
Reveal correct answer

Correct answer: A

Explanation

Schedule Performance Index of .80 means the project is behind schedule. The closer to “1” the SPI is the better the project. 2 is incorrect. An SPI of .80 means the project is behind schedule, not ahead. 3 is incorrect. While the project likely will result in being over budget due to the labor demands to complete the project, the SPI deals with the project schedule. 4 is incorrect. AN SPI does not reflect the percent complete of the project.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need