Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 35

The project charter should always address all of the following except for which one?
  • A Project purpose
  • B Assigned project manager and authority level
  • C Summary budget
  • D Project team members
Reveal correct answer

Correct answer: D

Explanation

Project team members are not identified in the project charter. 1 is incorrect; the project charter does identify the project purpose 2 is incorrect; the project does identify the project manager and the authority level 3 is incorrect; the summary budget is identified.