Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 35
The project charter should always address all of the following except for which one?
- A Project purpose
- B Assigned project manager and authority level
- C Summary budget
- D Project team members
Reveal correct answer
Correct answer: D
Explanation
Project team members are not identified in the project charter. 1 is incorrect; the project charter does identify the project purpose 2 is incorrect; the project does identify the project manager and the authority level 3 is incorrect; the summary budget is identified.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.