Certified Associate In Project Management CAPM · Free Practice Question Medium
Question 14
Bill is the project manager for a boxing gym with locations across the country. He is in the middle of a project that is putting new punching bags in each location. Because of the number of bags and the number of gyms involved, there are several stakeholders involved. What is the main benefit of the identify stakeholder process?
- A It enables the project sponsor to visualize the best way to allocate resources to the project.
- B It enables the project manager to assign the project team to the appropriate stakeholder group.
- C It enables the project manager to design a practical matrix management approach.
- D It enables the project team to identify the appropriate level of engagement for each stakeholder group.
Reveal correct answer
Correct answer: D
Explanation
Identifying and analyzing stakeholders' needs allows the team to determine and abide by the appropriate level of engagement for each stakeholder group. A project manager does not assign project team members to stakeholders. The project sponsor does not allocate project resources. Although a project exists in a matrix organization or a functional organization, the project manager does not design either. PSM13.4.152Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
