Prince2 7 Foundation · Free Practice Question Easy
Question 8
Which of the following is a part of the change theme?
- A To identify, assess and control uncertainty within the project
- B To establish a coding system for all components of the project's products
- C To define the means of delivering the products
- D To produce a benefits management approach
Reveal correct answer
Correct answer: B
Explanation
OBJ 3.6.1: The identification of project products involves configuration management, which is a part of the change theme. The purpose of the change theme is to identify, assess, and control any potential and approved changes to the project baselines.Discussion