Question 35
Which document is used during the project closure to review how the project performed against its intended objectives?
- A Change control approach
- B End project report
- C Quality management approach
- D Project brief
Reveal correct answer
Correct answer: B
Explanation
OBJ 3.7.1: An end project report is used during project closure to review how the project performed against the version of the project initiation documentation (PID) used to authorize it. It also allows the passing on of any lessons that can be usefully applied to other projects and provides details of unfinished work, ongoing risks, or potential product modifications to the group charged with future support of the project product in its operational life.Discussion