Question 24
Which statement about the project support role is CORRECT?
- A It can be performed by the project manager
- B It is an optional role for a PRINCE2 project
- C It produces checkpoint reports for the project manager
- D It can be combined with the project assurance role
Reveal correct answer
Correct answer: A
Explanation
OBJ 3.2.3: Project support is the responsibility of the project manager. The project support role defaults to the project manager if not otherwise allocated. The role of project support is not optional, but the allocation of a separate individual or group to carry out the required tasks is. If required, the project manager can delegate some of this work to a project support role that may include providing administrative services or advice and guidance on the use of project management tools. It could also provide specialist functions to a project such as planning or risk management.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.