Question 10

Which of the following is an objective of the controlling a stage process?
  • A To ensure that there is authority to initiate the project
  • B To ensure that all benefits have been achieved
  • C To act as a link between those managing the project and those creating products
  • D To capture the customer's quality expectations
Reveal correct answer

Correct answer: C

Explanation

OBJ 4.2: The objective of the controlling a stage process is to act as a link between those managing the project and those creating products. The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need