Question 4
You are configuring project metrics for dashboards in Azure DevOps. You need to configure a chart widget that measures the elapsed time to complete work items once they become active. Which of the following is the widget you should use?
-
A
Burndown
-
B
Cumulative Flow Diagram
-
C
Burnup
-
D
Cycle time
Reveal correct answer
Correct answer: D
Explanation
Cycle time measures the time it takes for your team to complete work items once they begin actively working on them.
Reference:
https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead-time?view=azure-devops&viewFallbackFrom=vsts