LEED Green Associate · Free Practice Question Easy

Question 31

Which of the following is excluded from Materials and Resources credit category calculation?

  • A

    Concrete slabs and columns.

  • B

    Gypsum board and insulation.

  • C

    Interior glazing and partitions.

  • D

    Plumbing and electrical works.

Reveal correct answer

Correct answer: D

Explanation

MEP works are not part of the calculations under materials and resources credit category.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.