LEED Green Associate · Free Practice Question Easy
Question 17
What is the most viable method to divert construction waste?
-
A
Source Reduction
-
B
Reused Waste
-
C
Waste-to-Energy
-
D
Recycling Waste
Reveal correct answer
Correct answer: A
Explanation
The most viable method to divert waste is to avoid the unnecessary waste generation by involving the source reduction strategies during the early phases of design, and to continue manufacturing and procurement to allow for exact sizes and proper selection of deliverables. Smaller packages and concentrated products typically use fewer materials and less energy to manufacture and transport.Discussion