Certified Information Systems Auditor CISA · Free Practice Question Easy
Question 69
What is the purpose of the risk assessment prior to the audit?
- A a) To detect instances of fraud and irregularities
- B b) To determine the audit budget
- C c) To evaluate the effectiveness of internal controls
- D d) To allocate audit resources based on risk levels
Reveal correct answer
Correct answer: D
Explanation
Correct answer: d) To allocate audit resources based on risk levels Explanation: The risk assessment prior to the audit helps in identifying areas of high risk and allocating audit resources accordingly to ensure effective coverage.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.