Certified Information Systems Auditor CISA · Free Practice Question Easy

Question 104

All of the following activities take place in the post-implementation phase EXCEPT:
  • A System adequacy
  • B Identification of issues/problems
  • C Security review
  • D Requirements gathering
Reveal correct answer

Correct answer: D

Explanation

Correct Answer:

Requirements gathering is correct. Gathering requirements takes place early in the SDLC, during the requirements definition phase.

Incorrect Answers:

All other answers are incorrect. These all are activities that occur after implementation.