Certified Information Security Manager CISM · Free Practice Question Easy
Question 55
What is the MOST suitable change management process for managing emergency program changes?
- A A. A thorough documentation process before implementing the change
- B B. No documentation required for emergency changes
- C C. Documentation can be compiled after change implementation
- D D. The change should be implemented without any formal process
Reveal correct answer
Correct answer: C
Explanation
Correct Answer: C. Documentation can be compiled after change implementation Explanation: In emergency situations, where immediate action is necessary, the focus is on addressing the issue promptly. Documentation can be compiled after the change implementation to ensure a swift response while still capturing essential information for future reference and analysis.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.