Certified Systems Engineering Professional Csep · Free Practice Question Easy
Question 14
[ID-3045] All the following are outputs of the project planning process, EXCEPT:
-
A
Project infrastructure needs
-
B
Breakdown structures
-
C
Systems Engineering Management Plan
-
D
Project authorization
Reveal correct answer
Correct answer: D
A.
These needs are outputs of the project planning process. They are also inputs to the infrastructure management process. See INCOSE SE Handbook 5th Ed. Section 2.3.4.1, p.71 and Section 2.3.3.2, p.55.
B.
Breakdown structure (e.g. work breakdown structure) is an output of the project planning process. See INCOSE SE Handbook 5th Ed. Section 2.3.4.1, p.71.
C.
The Systems Engineering Management Plan (SEMP) is an output of the project planning process. The SEMP has the purpose to establish how the systems engineering effort should integrate with the specific project. See INCOSE SE Handbook 5th Ed. Section 2.3.4.1, pp.71-73.
D.
The portfolio management process is the one responsible for authorizing and terminating projects. See INCOSE SE Handbook 5th Ed. Section 2.3.3.3, pp.58 and 59.
Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.