Question 1

Which of the following BA tasks needs a defined Stakeholder Engagement Approach as an input?

  • A

    Plan Stakeholder Engagement

  • B

    Analyze Current State

  • C

    Prepare for Elicitation

  • D

    Measure Solution Performance

Reveal correct answer

Correct answer: C

Explanation

Preparing for Elicitation requires a defined stakeholder engagement approach. "Plan Stakeholder Engagement" is the task that produces the engagement approach. Other two tasks do not depend on defined stakeholder engagement approach. refer to BABOK 3.2 Plan Stakeholder Engagement