Question 29

During the preparation for an elicitation activity, a business analyst (BA) realizes that the stakeholders have different levels of understanding of the project's context. What should the BA do to address this?
  • A Adjust the schedule to include more frequent breaks
  • B Use only written communication to ensure clarity
  • C Provide a detailed project overview to all participants
  • D Limit the number of participants to those with similar understanding
Reveal correct answer

Correct answer: C

Explanation

Providing a detailed project overview ensures that all participants have a consistent understanding of the project's context, facilitating more effective and productive elicitation sessions.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need