Of Capability In Business Analysis CCBA · Free Practice Question Medium
Question 29
During the preparation for an elicitation activity, a business analyst (BA) realizes that the stakeholders have different levels of understanding of the project's context. What should the BA do to address this?
- A Adjust the schedule to include more frequent breaks
- B Use only written communication to ensure clarity
- C Provide a detailed project overview to all participants
- D Limit the number of participants to those with similar understanding
Reveal correct answer
Correct answer: C
Explanation
Providing a detailed project overview ensures that all participants have a consistent understanding of the project's context, facilitating more effective and productive elicitation sessions.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.