Of Capability In Business Analysis CCBA · Free Practice Question Medium

Question 24

A business analyst has been working on a project for 6 months and has scheduled a formal walkthrough in 2 weeks. During this time, he has engaged with stakeholders to understand their intentions and concerns. What has he identified?
  • A Requirements and stakeholder concerns that have been stated and confirmed by all
  • B Requirements and stakeholder concerns that have been stated but not confirmed
  • C Stakeholder concerns that have been confirmed and documented
  • D Stakeholder concerns that have been mentioned but not confirmed
Reveal correct answer

Correct answer: B

Explanation

The primary purpose of discussing stakeholders' intentions at this stage is to gather and document requirements and concerns. However, these have not yet been validated or confirmed, necessitating further analysis and verification.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need