A business analyst is tasked with maintaining requirements for an ongoing project to enhance a customer portal. How can the BA ensure that any changes to the requirements are properly managed?
- A Implement a formal change control process.
- B Document all changes in a personal log.
- C Communicate changes informally during team meetings.
- D Wait for the project manager to approve all changes
Reveal correct answer
Correct answer: A
Explanation
Implementing a formal change control process for requirements updates ensures that changes are properly managed, documented, and approved. This process helps maintain consistency and traceability.Discussion