Question 17

What is the name of the process that avoids further competition under a framework agreement?

  • A

    Standing offer

  • B

    Direct call-off

  • C

    Closed system

  • D

    Blanket order

Reveal correct answer

Correct answer: B

Explanation

Direct call off is the act of placing an order under a framework agreement without having further competition.

Standing offer is an available offer.

Blanket order is another name of framework agreement

Closed system is a requirement of framework agreement. It is a system or process that, once started, does not allow new entrants.

Reference: CIPS study guide page 59-62

LO 1, AC 1.3