Istqb Certified Tester Foundation Level CTFL · Free Practice Question Easy

Question 76

Which of the following is a project risk?

  • A

    A module that performs incorrect calculations due to a defect in a formula

  • B

    A failed performance test

  • C

    An issue with the interface between the system under test and a peripheral device

  • D

    A problem with the development manager which is resulting in his rejecting all defect reports

Reveal correct answer

Correct answer: D