Question 64

Which of the following statements is true within an Agile team?

  • A

    Release planning explains accurately the prerequisites for releasing an increment

  • B

    Release planning meetings focus on acceptance criteria while iteration planning meetings focus on regression tests.

  • C

    Release plans are high-level level while iteration plans are low-level

  • D

    Release plans are low-level level while iteration plans are high-level

Reveal correct answer

Correct answer: C

A.

Is incorrect because an increment is linked to an iteration, not a version.

B.

Is incorrect because an iteration meeting focuses on tasks to be performed by the team.

C.

Is correct because release planning uses roughly estimated items, while iteration planning requires much greater estimation detail.

D.

s incorrect because, during the release meeting, the team has not completely thought about how to implement the backlog items.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need