Question 5
The project team primarily consists of:
- A Only business analysts
- B Business analysts, developers, testers, project manager
- C Only developers
- D Business representatives
Reveal correct answer
Correct answer: B
Explanation
Project team roles also vary depending upon the context and approach adopted for the project. Key roles include the project manager, the business analyst, developers and software testers. Business, solution and technical architects support the project work and ensure adherence with architectural principles and standards. Representatives from the project support office ensure that the work aligns with project standards.Discussion