SAFE Scrum Master Ssm · Free Practice Question Easy
Question 17
What are two outputs of the PI Planning ?
-
A
Team Backlog and Top 10 Features.
-
B
ART Planning Board and Team Backlog.
-
C
ART Planning Board and ART PI Objectives.
-
D
Porfolio Backlog and Team Backlog.
Reveal correct answer
Correct answer: C
Explanation
A successful PI Planning Event delivers two primary outputs:
Committed PI objectives: A set of SMART objectives that are created by each team with the business value assigned by the Business Owners;
ART Planning Board: Highlighting the new feature delivery dates, feature dependencies among teams and relevant Milestones.