SAFE Scrum Master Ssm · Free Practice Question Medium

Question 15

Which activities could a Scrum Master and Team focus on for the first Team breakout session of PI Planning ?     

  • A

    Create the Team's draft PI Objectives and Begin identifying Team dependencies.     

  • B

    Begin identifying Team dependencies and Plan each Iteration's details.   

  • C

    Create the Team's draft PI Objectives and Plan each Iteration's details.   

  • D

    Get Business values assigned to PI Objectives.   

Reveal correct answer

Correct answer: A

Explanation

In the first Team Breakout session of PI Planning, Team and the Scrum Master focus on creating the Team's draft PI Objectives and begin identifying dependencies. 

   

Study Guide: Here's the SAFe 6.0 article with complete explanation: https://www.scaledagileframework.com/pi-planning/

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need