SAFE Scrum Master Ssm · Free Practice Question Easy
Question 11
In SAFe 6.0, which activity is a Scrum Master's responsibility ?
-
A
Coordinating with other Teams.
-
B
Prioritizing the Team Backlog.
-
C
Facilitating the Coach Sync.
-
D
Owning the Team Sync.
Reveal correct answer
Correct answer: A
Explanation
Coordinating with the other Teams is in responsibility of a Scrum Master.
Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.