SAFE Scrum Master Ssm · Free Practice Question Easy
Question 1
What is considered an anti-pattern for the Iteration Retrospective?
- A Adding improvement items to the Team Backlog
- B Choosing an action item for another Team
- C Discussing Iteration metrics during the retrospective
- D Focusing on what to preserve as well as what to improve
Reveal correct answer
Correct answer: B
Explanation
Choosing an action item for another Team is not an expected activity performed in iteration retrospectives.Discussion