Question 7
The Requirements Management Phase is responsible for which of the following activities?
-
A
Implementing new requirements
-
B
Disposal of resolved requirements
-
C
Generating new requirements
-
D
Assessing the requirement's impact on the current ADM phase
-
E
Ensuring the (re-)prioritization of requirements by the architects and stakeholders
Reveal correct answer
Correct answer: E
Explanation
TOGAF® Standard - Architecture Development Method
Chapter 13: ADM Architecture Requirements Management
13.3 Steps
The phase adds requirements and re-assesses priorities.