Question 6

An urgent Work Item emerges and the WIP Limit is reached, what should the team do?

  • A

    Adjust the WIP Limit and add the Work Item

  • B

    Add the Item to the Product Backlog

  • C

    Nothing, add the Work Item as an exception

Reveal correct answer

Correct answer: C

Explanation

When something really urgent occurs, for example, a production bug it is better to add it as an exception rather than changing the WIP Limits. WIP Limits are used to optimise flow. If you would change WIP Limits due to an urgent production bug the team might miss the chance to improve their flow.