PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy
Question 35
Which estimation technique relies on information from similar projects?
- A Bottom-down estimation
- B Three-point estimation
- C Analogous estimation
- D Delphi estimation
Reveal correct answer
Correct answer: C
Explanation
Three-point estimating involves best case, worst case, and most likely estimates. Delphi estimation is based on a consensus of anonymous estimates from experts. There is no such thing as bottom-down estimation. Analogous estimation utilizes information from previous, similar projects.Discussion