PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 35

Which estimation technique relies on information from similar projects?
  • A Bottom-down estimation
  • B Three-point estimation
  • C Analogous estimation
  • D Delphi estimation
Reveal correct answer

Correct answer: C

Explanation

Three-point estimating involves best case, worst case, and most likely estimates. Delphi estimation is based on a consensus of anonymous estimates from experts. There is no such thing as bottom-down estimation. Analogous estimation utilizes information from previous, similar projects.