PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy

Question 28

You have been assigned to a new project, analyzing a change to an existing business system. Which of the following will be MOST useful to you?
  • A The project charter for the new project.
  • B The interrelationship diagram for the project.
  • C The weighted ranking matrix from the business case.
  • D The project's capability table.
Reveal correct answer

Correct answer: D

Explanation

The project charter includes an overview of high-level requirements, the business case, and project objectives. An interrelationship diagram is an analysis of a complex problem, probably used to decide which existing business system needs a change. The weighted ranking matrix in the business case shows alternative solutions which were considered. The capability table shows desired capabilities or capability gaps, and will be the most useful.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.