PMI Professional In Business Analysis PMI Pba · Free Practice Question Medium
Question 15
Working in an organization with a prescribed project management methodology, business analysis planning:
- A Is less significant than in an unstructured environment because the business analyst can choose any deliverables.
- B Is unnecessary because the methodology includes the business analysis plan.
- C Is required, but should be easier because some of the business analysis work is included in the overall project plan.
- D Is more significant than in an unstructured environment because the business analysis plan requires specific deliverables.
Reveal correct answer
Correct answer: C
Explanation
Whenever you are assigned to work on a project that is using a project management methodology, business analysis planning should be a little easier than in an unstructured environment because the methodology probably includes some tasks related to analysisDiscussion