PMI Professional In Business Analysis PMI Pba · Free Practice Question Easy
Question 4
The solution has been completed and tested. The project manager has asked you to show it to the business stakeholders before implementation. One of the key stakeholders finds a serious problem. What should you do?
- A Assess the impact of the problem.
- B Tell the stakeholder you will develop a workaround for him.
- C Talk with the development team and ask them to make a change.
- D Tell the project manager the implementation must be delayed.
Reveal correct answer
Correct answer: A
Explanation
It is possible that a serious problem might affect your implementation schedule. You may need to develop a workaround or request a change. However, before doing any of these, you need to assess the impact in order to determine the best course of action.Discussion