Certified Information Systems Auditor CISA · Free Practice Question Easy

Question 98

What are the two types of risk assessment used in auditing?
  • A Cost and mitigation
  • B Qualitative and quantitative
  • C High- and low-risk assessment
  • D Threat and impact
Reveal correct answer

Correct answer: B

Explanation

Correct Answer:

Qualitative and quantitative is correct answer. These are various terms associated with risk, but the two types of risk assessment commonly used are qualitative and quantitative assessments.

Incorrect Answers:

All other answers are incorrect.