Question 33

Which Roadmap does provide a longer-term (often multiyear) view, showing the key milestones and deliverables needed to achieve the solution vision over time?
  • A The Iteration
  • B The PI Roadmap
  • C The Solution Roadmap
  • D IP within PI
Reveal correct answer

Correct answer: C

Explanation

These are the SAFe 6.0 Planning Horizons:

  • Portfolio Roadmap: 1~3 Year forecast

  • Solution Roadmap: 1~3 Year forecast

  • PI Roadmap: 6~9 Month forecast (2~3 PIs typical)

  • PI Plan: 8~12 Week plan

  • Iteration Plan: 1~2 Week plan

  • Daily Plan: 1 Day plan


Study Guide: Here's the SAFe 6.0 article with the complete explanation: https://scaledagileframework.com/roadmap/

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need