SAFE Product Ownerproduct Manager POPM · Free Practice Question Easy

Question 32

What is a PI Planning input that demonstrated how Product Management plans to accomplish the vision?
  • A The Top 10 Features
  • B ART Backlog
  • C Business Context
  • D ART Planning board
Reveal correct answer

Correct answer: A

Explanation

The Product vision briefing(s) preparaded by Product Management including the top 10 Features in the ART Backlog.


Study Guide: Here's the Scaled Agile SAFe 6.0 article with the complete explanation: https://scaledagileframework.com/pi-planning/