Question 28

Which role ensures that the ART has the Vision and Backlog needed to engage in PI Planning successfully?

  • A

    Release Train Engineer

  • B

    Product Owner

  • C

    Lean-Agile Center of Excellence

  • D

    Product Management

Reveal correct answer

Correct answer: D

Explanation

Product Management is responsible for the overall product strategy, including the vision, roadmap, and requirements. They work with the Release Train Engineer (RTE) to ensure that the ART has the necessary information to plan for the upcoming Planning Interval (PI).

The RTE is responsible for the overall flow of work through the ART Kanban, but they do not have a direct role in ensuring that the ART has the Vision and Backlog.

The Lean-Agile Center of Excellence (LACE) is responsible for providing guidance and support to the ART, but they do not have a direct role in ensuring that the ART has the Vision and Backlog.

The Product Owner is responsible for the team backlog, which is a list of stories and functionalities that the product should have. They work with the Product Management team to ensure that the backlog is aligned with the overall product strategy. However, the Product Owner does not have a direct role in ensuring that the ART has the Vision and Backlog.

The correct answer is Product Management.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need