SAFE Product Ownerproduct Manager POPM · Free Practice Question Easy
Question 20
What is one value of holding regular system demos?
-
A
Execution can be measured across the whole ART
-
B
Problems can be escalated to ART leadership
-
C
Bottlenecks can be identified early by the teams
-
D
Deliverables are reviewed with stakeholders
Reveal correct answer
Correct answer: D
Explanation
This is a tricky question which you'll probably have in the official exam : The System Demo is a cadence-based event where the ART demonstrates the working increment to stakeholders at the end of each iteration. The demo showcases the team’s progress, allowing stakeholders to provide feedback and identify areas for improvement.
The other options may seem all corrects but we're looking for the best answer here. According to the offcial documentation :
PI Planning Value : Teams commit to a set of objectives to be delivered in the PI
Coach Sync Value : The teams on the ART sync regarding the progress of the PI
System Demo Value : Deliverables are reviewed with stakeholders who provide feedback
Inspect and Adapt Value : The ART reviews and improves its process before the next PI