SAFE Product Ownerproduct Manager POPM · Free Practice Question Easy
Question 16
During which event does the team preview and elaborate on upcoming Stories
-
A
Backlog Refinement
-
B
PI Planning
-
C
Team Sync
-
D
Iteration Planning
Reveal correct answer
Correct answer: A
Explanation
Backlog Refinement is an iterative process where the Development Teams work with the Product Owner to refine the Product Backlog. This includes previewing and elaborating on upcoming Stories.
During Backlog Refinement, the team will:
Review the Product Backlog items.
Break down large items into smaller, more manageable stories.
Estimate the effort required to complete each story.
Define the acceptance criteria for each story.
Prioritize the stories.
By the end of Backlog Refinement, the team should have a clear understanding of the work that needs to be done in the upcoming iterations.
The other events listed do not involve previewing and elaborating on upcoming Stories.
PI Planning: PI Planning is an event where the ART plans the next Planning Interval (PI).
Team Sync: Team Sync is a daily event where the team meets to discuss their progress and to plan for the iteration Demo.
Iteration Planning: Iteration Planning is an event where the team plans the next iteration.