What is the relationship between the Sprint Backlog and the Product Backlog?

  • A

    There is a minor difference between both.

  • B

    There is no relationship.

  • C

    The Sprint Backlog is a subset of the Product Backlog

  • D

    The Product Backlog is a subset of the Sprint Backlog.

Reveal correct answer

Correct answer: C

Explanation

Sprint Backlog is the set of Product Backlog items selected for the Sprint.The Scrum Guide, Page 11