Certified Scrummaster CSM · Free Practice Question Easy
Question 14
The Sprint Backlog is owned by:
-
A
The Project Manager
-
B
The Product Owner
-
C
The Scrum Master
-
D
The Developers
Reveal correct answer
Correct answer: D
Explanation
The Sprint Goal is a commitment by the Developers The Scrum Guide, Page 11
Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.