Certified Scrummaster CSM · Free Practice Question Easy

Question 8

Which objectives are covered as part of Sprint Planning?

  • A

    Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to do it.

  • B

    Updating the scope of the release with all sprints, end dates and costs.

  • C

    Reviewing obstacles towards the Product Goal.

  • D

    Calculating team velocity and adjusting team capacity accordingly.

Reveal correct answer

Correct answer: A

Explanation

Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint. This resulting plan is created by the collaborative work of the entire Scrum Team.The Scrum Guide, Page 8