Question 7

Which of the following would NOT be discussed at the Sprint Retrospective ?

(Choose two answers)

  • A The features delivered in the Sprint.
  • B The Definition of Done.
  • C Improvements to the working process.
  • D Sprint Backlog for the upcoming Sprint.
  • E Team interactions.
Reveal correct answers

Correct answers: A, D

Explanation

According to the Scrum Guide 2020, the Sprint Retrospective is an opportunity for the Scrum team to self-assess and reflect on how to improve its work process. It focuses on inspecting the entire development process, including team member interactions, development practices, tools used, and relationships with stakeholders.

However, the features delivered in the Sprint and the Sprint Backlog for the next Sprint are not discussed during the Sprint Retrospective. These elements are instead addressed during the Sprint Review, where the team presents the completed features to the development team, stakeholders, and the Product Owner.

The Sprint Retrospective is specifically dedicated to the continuous improvement of the team's development process. It allows the team to reflect on what went well, what didn't work, and how it can improve for the next Sprint. Topics discussed may include encountered obstacles, work practices, interpersonal relationships, tools used, and any other aspect of the development process.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need