Professional Scrum Master I PSM I · Free Practice Question Easy

Question 92

True or False: A Scrum Team can include an undone Product Backlog item in the Increment if they document what is left to do.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

The definition of an Increment in Scrum is that it must be "Done." That means it must meet the Definition of Done established by the Scrum Team. If a Product Backlog item is "undone" or incomplete according to this definition, it cannot be included in the Increment, regardless of whether what's left to do is documented. This is to ensure transparency about the completeness and releasability of work, and to maintain quality and value of the Increment.